Permits to work: a guide for FM leaders
In brief

A permit to work is a formal way to control higher-risk work, such as hot work, confined space entry and jobs that need isolation. This guide explains when permits are used, why a permit is not a risk assessment, the roles, contents, isolation, handover, contractors and review. It is general information, not technical advice.

Permits to work: a guide for FM leaders cover

Some jobs in a building are too risky to start on a verbal go-ahead. Hot work, entering a tank or duct, work on isolated electrical or mechanical plant and jobs where several teams or contractors affect one another all need tighter control. A permit to work is one way to provide it, and FM leaders are often the people who set up the system, keep it working and answer for it when something goes wrong.

This guide explains what a permit to work is, when one is used, why a permit is not a risk assessment, the roles involved, what a permit should contain, isolation and reinstatement, shift handover and handback, contractors, and training and review. It draws on guidance from the Health and Safety Executive (HSE), including its guidance on permit-to-work systems, which HSE says is relevant to any industry that uses permits.

The core idea: A permit brings the risk assessment to the people doing the work. It only works if everyone involved understands it and uses it as intended.

What the guide covers

  • What a Permit to Work Is
  • When a Permit Is Used
  • A Permit Is Not a Risk Assessment
  • Roles and Responsibilities
  • What a Permit Should Contain
  • Isolation and Reinstatement
  • Shift Handover, Suspension and Handback
  • Contractors and Visiting Workers
  • Training, Monitoring and Review
  • Common Mistakes

What a Permit to Work Is

HSE describes a permit to work as a formal system that sets out what work will be done, when, and which parts of the plant or equipment are safe to work on. A responsible person assesses the work and checks safety at each stage, and the people doing the work sign to confirm they understand the risks and precautions.

In practice: Ask where permits are issued at your sites, who issues them and where completed ones are kept.

When a Permit Is Used

HSE says standard instructions are enough for most tasks, but higher-risk work needs more control. Its examples include hot work such as welding, entering vessels, cutting into pipework that carries hazardous substances and work that needs electrical or mechanical isolation.

In practice: Write down which jobs at your sites need a permit, and check that contractors know the list.

A Permit Is Not a Risk Assessment

HSE says a permit does not replace a proper risk assessment. Its value is in bringing that assessment to the front line, where the work happens. HSE’s permit guidance adds that a permit does not make a job safe by itself: safety depends on how the work is prepared, supervised and carried out, and isolations or barriers may also be needed.

In practice: Take a completed permit and check that the controls it lists were in place when the work started.

Roles and Responsibilities

HSE’s permit guidance describes several roles and notes that titles can differ between sites. The roles matter more than the names:

In practice: Write down who holds each role at each site, and who covers when they are absent.

What a Permit Should Contain

HSE’s permit guidance sets out what a permit should include:

In practice: Compare your permit with this list and ask the people who use it what is unclear or missing.

Isolation and Reinstatement

HSE’s human factors guidance points to its guidance on the safe isolation of plant and equipment, and says failures during isolation and reinstatement are a main cause of loss-of-containment incidents. That guidance is aimed mainly at the oil, gas and chemical industries but is relevant to any industry that carries out isolations. HSE also publishes guidance on safe working practices for electrical work, written for people who work on or near electrical equipment and for managers and supervisors who influence how it is maintained or operated.

In practice: Pick a recent isolation and check who applied it, who checked it and who removed it.

Shift Handover, Suspension and Handback

HSE says that when work runs across more than one shift, the plant should be left in a safe state and the next shift given clear instructions. HSE’s permit guidance adds that the incoming shift should know about outstanding jobs and the plant’s status, and that the incoming issuing authority signs to continue the permit.

In practice: Look at how a job that runs across two shifts is handed over, and where that is written down.

Contractors and Visiting Workers

HSE’s brief guide to using contractors sets out steps for the client: identify the job, choose a suitable contractor, assess the risks, provide information, instruction and training, cooperate with the contractor, and manage and supervise the work.

In practice: Before the next job, walk the contractor through your permit process and ask them to explain it back.

Training, Monitoring and Review

HSE’s permit guidance calls training the foundation of a system. It should cover the principles, when permits apply, the types of document, responsibilities, the hazards and controls, and lessons learned. Competence should be tested and retested, records kept, and trainee issuers can have permits countersigned by experienced issuers for a period.

In practice: Put a date in the diary to audit your permit system, and ask someone independent to carry it out.

Common Mistakes

  • Assuming that issuing a permit makes a job safe
  • Signing permits without visiting the work site
  • Unclear roles, with overlaps or gaps in who is in charge
  • Permit overload at the start of a shift
  • Failing to link related or simultaneous permits
  • Not briefing contractors on how the system works
  • Training people on electronic permit software but not on the permit process
  • Leaving suspended permits open without checking the isolations before work restarts

Most of these are avoidable. Keep the system simple, train the people who use it and check that it works in practice.

Frequently asked questions

What is a permit to work?

A formal system, described in HSE guidance, that records what work will be done, where, by whom and with what precautions, so that higher-risk work is controlled and communicated.

Does a permit make a job safe?

No. HSE says a permit does not replace a risk assessment. The controls have to be in place on site and understood by everyone involved.

Which jobs need a permit?

Your risk assessments and procedures decide. HSE’s examples include hot work, confined space entry, work needing electrical or mechanical isolation and work at height.

Who can issue a permit?

The people your system names and trains. HSE’s guidance describes roles such as the issuing authority and says competence should be tested and records kept.

What if the work runs over more than one shift?

HSE says to leave the plant in a safe state and give the next shift clear instructions. The incoming issuing authority signs to continue the permit.

Do contractors follow our permit system?

HSE’s permit guidance says everyone working on site, including contractors, has duties under the system and needs to understand it, and that contractor management should train its people.

Can permits be electronic?

HSE’s guidance considers electronic systems. It says to assess the changeover, train people on the process as well as the software, and check safeguards such as secure signatures.

How often should we review the system?

HSE’s permit guidance calls for regular audits by competent people, preferably from outside the site, and system reviews at least every three years. In our view, review sooner after an incident.

Key takeaways

  • HSE describes a permit to work as a formal system that sets out what work will be done, when, and which plant is safe to work on, with a responsible person checking safety at each stage
  • A permit does not replace a risk assessment or make a job safe by itself, so the controls have to be in place on site and understood by everyone involved
  • HSE’s guidance lists roles such as the issuing authority, the performing authority, the area authority and the isolating authority, and names unclear roles as a common failure
  • Plan shift handover, suspension and handback, because HSE’s guidance says a suspended permit remains live until it is cancelled, so isolations may still be in place
  • Contractors have duties under the permit system and need to understand it, and everyone who issues or uses permits needs training, monitoring and regular review

Final thoughts

A permit to work is a tool for controlling higher-risk work and passing the controls to the people doing it. It does not replace the risk assessment, and it works only when roles, isolation, handover and training are clear.

Decide which jobs need a permit, name the roles, check your form against HSE guidance, agree your isolation, handover and handback steps, brief contractors and audit the system. Take advice from a competent person on high-risk work.

Related reading

Who this resource is for

FM Directors, Heads of Facilities, engineering and operations managers, and health and safety leads who are responsible for controlling higher-risk work in occupied buildings, including work by contractors.

Talk to Maxwell Stephens

If you want to talk this through, contact Maxwell Stephens or call 0207 118 4848 to book a scoping call.

For help defining and filling a senior role, explore our Facilities Director recruitment service.

Last reviewed 29 November 2026. Laws, dates and figures change, so check the current position before you act. This resource is general information, not legal advice.