The British Library’s 2024 solar announcement forecast annual energy and carbon benefits. Its mix of heat-only and hybrid collectors needs precise, dated reporting.
Naked Energy’s 14 October 2024 announcement described a solar installation at the British Library’s St Pancras site, delivered with CBRE. The supplier reported 950 collectors across 712.5 square metres and forecast 216 MWh of energy and 55 tonnes of CO2 reduction annually.

Keep the forecast label
Those figures were an announcement forecast, not a measured annual result established by this article. The release described the project as the UK’s largest solar-heat installation at that time; it should not become an undated ranking of every installation today.
Distinguish heat-only and hybrid collectors
The manufacturer’s case-study page describes a mix of VirtuHOT and VirtuPVT equipment. The installation should not be described as though every collector generates both heat and electricity. The page lists 203 MWh of thermal output per year; that thermal measure is not directly interchangeable with an earlier total-energy figure.
The manufacturer links the installation to hot-water, space-heating and humidity-control needs at the library. That intended contribution does not establish that solar alone provides every environmental condition needed to preserve the collection.

The FM assessment
- Define the building’s actual heat and electrical demand.
- Check the project’s heritage, access and maintenance requirements.
- Record design assumptions and the metering needed to test them.
- Agree responsibility for controls, faults and performance review.
- Separate forecast savings from evidence collected after commissioning.
Avoid a universal product comparison
A carbon comparison needs an explicit area, useful-energy demand, baseline and calculation method. A supplier’s product-range comparison should not be applied to another estate without checking those assumptions.
FM reporting implications
- Attribute and date supplier figures.
- Keep thermal and electrical measures distinct.
- Check actual performance against the project’s own baseline.
From forecast to operation
The project illustrates the importance of matching a renewable system to the building’s use. Accurate FM reporting preserves the difference between specification, forecast and measured operation.
Next steps